Custer Parkway Newsletter

Post Date:04/17/2026 3:40 PM

11-10-2025 Custer Canyon Creek-01 

Paving work at Custer Parkway on the south side of Canyon Creek Drive will not continue for another two to three weeks due to ongoing work related to the gas main. Due to a conflict with a shallow gas main found during construction, Atmos needs to relocate its gas main across Custer Parkway on the south side of the Canyon Creek Drive intersection. Because of this, the removed pavement at this intersection will remain unfinished until Atmos completes its relocation work. Atmos currently estimates this work will take two to three weeks to complete, weather permitting.

For more information about the Custer Parkway Reconstruction Project, visit www.cor.net/CusterParkway.