Cotton Belt Trail

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

CottonBelt_LocationMap_042126

Cotton Belt Trail Corridor 

The Cotton Belt Trail will be a new regional trail which provides a connection between Plano and Fort Worth. The trail corridor generally follows a portion of the TEXRail commuter rail in Tarrant County as well as the DART Silver Line rail corridor in Dallas County and Collin County. Along the way the corridor links several key destinations and municipalities such as Downtown Grapevine, Old Town Coppell, Cypress Waters in Dallas, Downtown Carrollton, Addison Circle, UT Dallas and CityLine in Richardson, and Downtown Plano.

The total mileage of the corridor from Shiloh Station in Plano to the intersection with the DFW Discovery Trail (just west of Handley Ederville Rd. in Fort Worth) is approximately 57 miles. Concurrent with the DART Silver Line implementation, the City of Richardson and other communities along the corridor have partnered with the North Central Texas Council of Governments (NCTCOG) and DART to advance design and construction of the trail from DFW Airport to Plano. Additional information can be found on NCTCOG's webpage here.

Trail Implementation - DFW Airport to Plano

On October 11, 2018, NCTCOG's Regional Transportation Council (RTC) approved funding for engineering design of the trail from DFW Airport to Shiloh Road in Plano which is now complete. 

Currently portions of the trail corridor exist, such as a section of Spring Creek Trail in Richardson will serve as part of the Cotton Belt Regional Trail. Implementation of the remaining sections of trail are split into three phases:

  • Phase 1 (Complete): Construction consisting of several Cotton Belt Trail bridges was completed concurrently with the Silver Line rail project.
  • Phase 2 (Current Construction): DART began construction in Spring 2025 for than 11 miles of additional trail and bridge segments from Addison to Plano. This phase constructs continuous trail through Richardson with a construction cost over $24 million which is funded primarily through various federal funding awards.
  • Phase 3 (Future): Trail construction along the Silver Line commuter rail will complete the trail in Dallas and Addison and continue westward, occurring in the future once additional funding is secured. An additional 4.11 miles of planned trail alignment located outside of the rail right-of-way in Carrollton and Coppell will connect with the Cotton Belt Trail to form a continuous trail alignment between those cities.

The map below outlines sections of trail funded within each phase as of October 2025, including anticipated timelines on sections of Phase 3.

CottonBelt_CoridorMap_042026

Richardson Construction Updates

Construction on the Cotton Belt Trail in Richardson began in May 2025. The table below reflects construction activity from the most recent project newsletter. The latest and past newsletters are available at the bottom of this page. A link to view construction photos is available in each newsletter to see progress along the corridor.

Note: Completion dates shown are estimated construction end dates and do not indicate when segments will open to the public. Dates are also subject to change as construction advances.

LOCATION CONSTRUCTION ACTIVITY START FINISH STATUS
Waterview Pkwy Intersection Crossing work to begin once trail paving between Coit and Waterview is complete. Mar. 25, 2026 Nov. 2, 2026 20%
Waterview Pkwy. to Rutford Rd. Trail, fencing, and final clean-up is complete. Sept. 22, 2025 Apr. 30, 2026 100%
Rutford Rd. Intersection Completed in February. Final striping and 
signage remains.
Feb. 2, 2026 Jul. 31, 2026 99%
Rutford Rd. to Existing UTD Trail Trail is complete. Final clean up remains. Nov. 19, 2025 Jul. 31, 2026 99%
Existing UTD Trail to E. of Trestle Bridge Installation of RW3283 and drainage is complete. Construction under the KCS trestle remains. Mar. 2, 2026 Oct 5, 2026 35%
East of Trestle Bridge to Synergy / Renner Intersection Trail is 85% complete. Soil nail work under DART SL and CPKCS bridge completed 6/30. Phase 2 median work remains and will begin once the traffic signal is ready for activation. Landscaping scope continues. Nov. 3, 2025  Jul. 29, 2026 75%
Synergy Park Blvd / Point North Park Driveway Intersection Northbound sidewalk and ramp is complete. Signal poles have been erected; activation remains.  Dec. 1, 2025 Jul. 31, 2026 95%
Synergy Park Blvd / W. Renner Rd. Intersection Signal poles have been erected. Trail has been installed north of Renner Rd. Phase 2 median work remains and will begin once the traffic signal is activated.  Jan. 19, 2026 Jul. 31, 2026 70%
W. Renner Rd / Greenside Dr. Intersection Trail connections and median are complete. Stamped concrete, striping and signage remain. Jan. 19, 2026 Jul. 31, 2026 90%
South of Greenside Dr. Trail to bus stop is complete.  Mar 6, 2026 Aug. 30, 2026 50%
W. Renner Rd. to Custer Rd. Bridge Trail work ongoing. Culvert 1 installation ongoing. Apr. 8, 2026 Jan. 6, 2027 35%
Custer Rd. Bridge Bridge drainage began in June and will complete in July. Drilled shaft and MSE wall construction to begin mid-July. Mar. 30, 2026 Oct. 29, 2027 15%
Custer Rd. Bridge to Alma Rd. Trail subgrade work continues. Arch culverts foundation placement continues. Arch culverts placement anticipated end of July. Apr. 15, 2026 Feb. 19, 2027 30%
Alma Rd. Intersection No Work Oct. 14, 2026 Oct. 27, 2026 0%
Spring Creek Bridge Bridge deck and approach slab pours complete. Signage and railing installation remaining. Jun. 9, 2025 Aug 31, 2026 95%
Spring Creek Bridge to Red Moon Way Trail and sidewalk wall construction are ongoing. Jun. 9, 2025 Aug. 31, 2026 80%
West City Line Dr. Intersection Routh and City Line intersection are poured out. Fencing installation begins June 1st. Sept. 29, 2025 May 31, 2026 90%
West City Line Dr. to PGBT EB Frontage Trail pour completed. Signage and striping 
remain. Fencing installation to begin in July.
Jul. 7, 2025 Jul. 31, 2026 95%
PGBT EB Frontage / Routh East Dr. Intersection Trail pour completed. Signage, striping and installing signal poles remain. Sept. 10, 2025 Aug. 31, 2026 80%
PGBT EB Frontage to PGBT WB Frontage Scope is 100% complete. May 14, 2025 May 8, 2026 100%

View our latest progress photos here!

Newsletter Updates

June 2026 Newsletter 

May 2026 Newsletter

April 2026 Newsletter

March 2026 Newsletter

February 2026 Newsletter

January 2026 Newsletter

December 2025 Newsletter